Nordic Iron Ore AB secures the electricity supply
Nordic Iron Ore's application for the accessing up to 20 MW of power has received final approval from Svenska Kraftnät.
In June 2019, Nordic Iron Ore applied, via Västerbergslagens Elnät, for the possibility of drawing up to 20 MW for the future mining operations in Blötberget. Svenska Kraftnät has now, based on the plans in the area, assessed that the power take-off can be permitted.
"It is a very welcome message that we can now count on getting the electricity we need for the mining investment, especially as we are investing in building an environmentally friendly electrified mine." says the company's CEO Lennart Eliasson
During the processing of the case, Nordic Iron Ore has had the 50 kV line, that the power will be taken from, moved. The next step will be to design and erect a switchgear next to the future industrial area.